The warehouse is rented, with racking seven to nine meters tall. That once suited a range of 50-70 SKUs in large batches. Now there are around a thousand SKUs, batches are smaller, and the lower picking levels can't hold the whole matrix. The lifts run every day and slow every operation down. Records were kept in 1C and Excel, while the warehouse ran on paper, so goods moved faster than the records were updated.
The consequences named at the meetings were concrete: discrepancies between the records and the physical count, picking errors, customer claims.
From receiving goods to staff bonuses, with accounting and integration reviewed separately.
Discovery ran as a series of working meetings by process block, and the key meetings had written minutes. The as-is diagram shows the problems: which Excel files will disappear, which manual operations will be automated, which functions are missing today. Before finalizing the target scheme, the roadmap includes a mandatory on-site visit to the warehouse.
We discussed three schemes. Two-step receiving: receiving closes the supplier order, put-away is separate. One-step: one person receives and puts away at once. Hybrid: goods are received into an entry zone, and then several people take turns putting them away into storage. We chose the hybrid. The reason is a constraint: for one order the system creates one receipt document, and one person works with it. The hybrid gets around this with a partial receipt and a remainder on an internal transfer.
A remainder on the transfer gives sequential work by several people, not simultaneous. If simultaneity is what the client really needs, that is no longer standard functionality but a separate customization, and the estimate will change. We put this in the register as its own line with the status “to verify” and made it the first, blocking question to the client. That keeps the first-stage estimate accurate.
We compared the list of carriers available in Odoo, and there is no ready connector for a Ukrainian carrier among them. We agreed a fallback: a delivery method with a fixed price and a “waybill number” field. A full connector is outside the first stage and clearly marked as such: without test API access the estimate is unreliable.
We enter the batch number at the entrance. That way it doesn't get lost when several warehouse workers take turns putting a delivery away.
This is the first-stage plan. On the prototype, the put-away rules, the aisle sequence number and batch capture on the move from the entry zone to storage are already configured, and the prototype has been shown to the client.
We take your process and show what standard Odoo covers and what is really worth extending.